Chapter 5. Airworthiness Control Procedures


5.4  Joint DAR/TCCA Approval Projects

For Joint DAR/TCCA approval projects, in addition to the documentation required in a modification or repair approval application form, the following documentation shall be submitted with a request for review and approval:

  1. (Draft) LSTC, STC or RDC document;
     
  2. AE-100 Form Statement of Compliance (DAR-signed original, indicating delegated data approved, other data recommended for TCCA approval;
     
  3. Compliance Program (delegated elements signed off, other elements recommended for sign off);
     
  4. (Draft) Flight Manual Supplement (if applicable); and
     
  5. (Draft) Maintenance/Repair Manual Supplement.
Previous Page
Next Page
Date modified: