The following project in Prince Edward Island is receiving funding under the federal funding programs.
Funding Program: Canada Strategic Infrastructure Fund
Announcement: May 5, 2006
Estimated Total Project Cost: $19.6 Million
Federal Contribution: $7.5 Million
Project Completion: October 2009
The project consisted of nine project components involvingthe rehabilitation and reconstruction of approximately 22 km of highway along sections of Route 2, between the cities of Charlottetown and Summerside, in addition to a non-signalized “T” intersection being changed into a roundabout, and the construction of new turning lanes at another project component location.